Works on Cathedral Drive Begin

Work has started on the upgrade of the New England Highway between Hampton and Geham. Design and construction is being undertaken according to recommendations made in the independent report handed to Minister Wallace in May – more in this story from Tuesday’s Toowoomba Chronicle.

See the table below for Main Roads’ design and construction timetables.

Proposed Staged Construction

  • Section A1 (Munro Road to Collingwood Road) – 2.5km
  • Section A2 (Geham Tip to Pioneer Road) – 2.0km
  • Section B (Collingwood Road to Pioneer Road) – 5.5km
Design Schedule

  • Section A1 – complete by end June 2010
  • Section A2 – complete by mid July 2010
  • Section B – start mid July and complete end of October 2010
Construction Timelines

  • Section A1 – August 2010  through to November 2010
  • Section A2 – September 2010  through to December 2010
  • Section B – February 2011 through to May 2011